Per Ordinance 183893, the Order to Comply is dismissed when the Department files a County Recorder certificate (§91.9306.6) and the design professional (a California civil or structural engineer or architect per §91.9305.1) puts a statement on the approved plans (§91.9310.2).

Last updated: August 27, 2026

What are the official close-out requirements?

Per Ordinance 183893, two official close-out items dismiss the Order:

Close-out requirementOrdinance sectionWho provides it
County Recorder certificate§91.9306.6Department files with County Recorder
Statement on the approved plans§91.9310.2California civil or structural engineer or architect (§91.9305.1)

How does the close-out process work?

After construction completion, the design professional puts a statement on the approved plans per §91.9310.2. The Department then files a County Recorder certificate per §91.9306.6. These two official close-out items dismiss the Order.

Frequently asked questions

What is required to dismiss a soft-story retrofit Order?

Per Ordinance 183893, the Department files a County Recorder certificate (§91.9306.6) and the design professional (a California civil or structural engineer or architect per §91.9305.1) puts a statement on the approved plans (§91.9310.2) to dismiss the Order to Comply.

How long does Order dismissal take?

Dismissal timing depends on LADBS workload and completion of the official close-out requirements. Owners should complete construction and coordinate with the design professional promptly to avoid ordinance deadline violations.