LADBS Compliance Timeline Soft-Story: from the receipt of the Order to Comply, the owner has 2 years to submit proof of previous retrofit, or plans to retrofit or demolish; 3.5 years to obtain permit to start construction or demolition; and 7 years to complete construction (LADBS Soft-Story Retrofit Program). Ordinance 184081 amended §91.9305.2 of Ordinance 183893 “to adjust time limits”: “Within two (2) years after service of the order described in Section 91.9306, submit to the Department for review and approval” a structural analysis and plans, or plans for the demolition of the building; “Within three and a half (3.5) years after service of the order, obtain all necessary permits for rehabilitation or demolition”; “Within seven (7) years after service of the order, complete construction or demolition work under all necessary permits.” Time limits for compliance shall be based on the service date of the original order from the Department. Transfer of title shall not change compliance dates. Those ordinance deadlines and the LADBS Soft-Story Retrofit Program path set the city timeline; a lender PML/SEL report alone does not satisfy it.

Per the DBS Soft Story Retrofit Program, the property owner must comply with the ordinance within the following time limit from the receipt of the Order to Comply: 2 years: Submit proof of previous retrofit, or plans to retrofit or demolish; 3.5 years: Obtain permit; 7 years: Complete construction. Owners must retain a California civil or structural engineer or architect (per Ordinance 183893 §91.9305.1). Per the ordinance, §91.9306.6 lists County Recorder recordation at order service and a later certificate terminating the recorded status after demolition, not-in-scope finding, or structural alterations or analysis. §91.9310.2 lists engineer/architect statements on the approved plans (design-time text, not an Order-dismiss act). §91.9305.1 lists civil or structural engineer or architect.

Last updated: November 28, 2026

What are the soft-story compliance deadlines?

Per the DBS Soft Story Retrofit Program, the property owner must comply with the ordinance within the following time limit from the receipt of the Order to Comply:

Deadline from receipt of Order to ComplyRequirement
2 yearsSubmit proof of previous retrofit, or plans to retrofit or demolish
3.5 yearsObtain permit to start construction or demolition
7 yearsComplete construction

Source: DBS Soft Story Retrofit Program

When did LADBS send the Orders to Comply?

Per the LADBS Soft-Story Retrofit Program, each property owner of an in-scope building “will be sent an order to comply.” “These orders will be sent accordingly based on the following priorities” (start date of sending out orders for each category). Per Ordinance 184081, time limits for compliance shall be based on the service date of the original order from the Department.

PriorityCategoriesStart date of sending out Orders
I. Buildings with 16 or more dwelling units3-story and aboveMay 2, 2016
I. Buildings with 16 or more dwelling units2-storyJuly 22, 2016
II. Buildings with 3 or more storieswith less than 16 unitsOctober 17, 2016
III. Buildings not falling within the definition of Priority I or IIwith 9-15 unitsJuly 24, 2017
III. Buildings not falling within the definition of Priority I or IIwith 7-8 unitsAugust 21, 2017
III. Buildings not falling within the definition of Priority I or IIwith 4-6 unitsSeptember 25, 2017
III. Buildings not falling within the definition of Priority I or IICondos/CommercialNovember 6, 2017

Source: LADBS Soft-Story Retrofit Program

What are the typical timeline phases?

Owners should start early to allow for engineer retention and retrofit design, permit application and LADBS plan check review, construction, and document review. §91.9310.2 lists engineer/architect statements on the approved plans (design-time). §91.9306.6 lists Department County Recorder recordation and a later terminating certificate after alterations or analysis per Ordinance 183893. These phases must fit within the deadlines above. The ordinance does not list a lender PML/SEL as what closes the Order.

What happens if the deadline is missed?

Missing the compliance deadline can result in enforcement actions by LADBS.

Compliance statusOutcome
Completed before deadlineAfter alterations/analysis: Department may file certificate terminating recorded status (§91.9306.6)
In progress with permitDemonstrate progress to LADBS

Frequently asked questions

What is the LADBS compliance timeline for soft-story retrofit?

Per the DBS Soft Story Retrofit Program, the property owner must comply with the ordinance within the following time limit from the receipt of the Order to Comply: 2 years: Submit proof of previous retrofit, or plans to retrofit or demolish; 3.5 years: Obtain permit; 7 years: Complete construction. Per Ordinance 183893, §91.9306.6 lists County Recorder recordation at order service and a later certificate terminating the recorded status after demolition, not-in-scope finding, or structural alterations or analysis. §91.9310.2 lists engineer/architect statements on the approved plans (design-time text, not an Order-dismiss act). §91.9305.1 lists civil or structural engineer or architect.

Can the compliance deadline be extended?

Extension criteria and procedures are established by ordinance and LADBS policy.

What are the typical timeline phases?

Owners should start early to allow for engineer retention and retrofit design, permit application and LADBS plan check review, construction, and document review. §91.9310.2 lists engineer/architect statements on the approved plans (design-time). §91.9306.6 lists Department County Recorder recordation and a later terminating certificate after alterations or analysis per Ordinance 183893. These phases must fit within the deadlines above. The ordinance does not list a lender PML/SEL as what closes the Order.

What happens if the deadline is missed?

Missing the compliance deadline can result in enforcement actions by LADBS.

When did LADBS start sending soft-story Orders to Comply?

Per the LADBS Soft-Story Retrofit Program, orders went out by priority: Priority I (16 or more dwelling units) 3-story and above from May 2, 2016 and 2-story from July 22, 2016; Priority II (3 or more stories, less than 16 units) from October 17, 2016; Priority III with 9-15 units from July 24, 2017, 7-8 units from August 21, 2017, 4-6 units from September 25, 2017, and Condos/Commercial from November 6, 2017.